Setting the printer the paper size for the Gantt are similar to how they are set for the Network Views. We recommend that you print Gantt view on an 11x17 or an A3 sized paper for best results. vPlanner will try to fit the grid columns first and will scale the timeline to fit the remaining space adjusting the visible date range settings by switching automatically to Years, Months, or Days depending on how space is available to fit the text. This does not affect the Gantt View itself, just the printed version.

Figure 99 – Gantt Print Preview